PUNJAB MUNICIPAL SERVICES IMPROVEMENT PROJECT (PMSIP) |
|||||
|
SUB-PROJECTS (WORKS) AWARD STATUS 2006 - 2007 |
|||||
| Sr. # | SUB-PROJECT | CONTRACTOR'S NAME | CONTRACT SIGNED ON |
COMPLETION PERIOD (DAYS) |
REMARKS |
| 1 | Extension-Improvement of Water Supply Scheme Kasur | M/s Ch. Amjad Ali | 09/04/2006 | 730 | Works in progress |
| 2 | Rehabilitation of Water Supply Scheme-Bhalwal | M/s Global Construction Company | 09/04/2006 | 540 | Works in progress |
| 3 | Improvement of Water Supply Scheme Pind Dadan Khan | M/s MAT Technologies | 09/06/2006 | 450 | Works in progress |
| 4 | Improvement and Extension of Water Supply Scheme Jhelum | M/s Unique Construction Company | 09/07/2006 | 730 | Works in progress |
| 5 | Extension-Improvement of Water Supply Scheme Toba Tek Singh | M/s Rising Sun Construction | 29/12/2006 | 540 | Works in progress |
| 6 | Improvement of Roads in Shorkot | M/s Syed Hassan Mahmood and Company | 30/04/2007 | 270 | Work in progress |
| 7 | Extension/Improvement of Water Supply Scheme Chakwal | M/s MAT Technologies | 19/06/2007 | 365 | Works in progress |
| 8 | Extension-Improvement of Water Supply Scheme Mailsi | M/s SIEMENS Pakistan Engg. Co. | 13/07/2007 | 730 | Works in progress |
| 9 | Improvement of Circular Road Pind Dadan Khan | M/s Malik Corporation | 17/08/2007 | 270 | Works in progress |
| 10 | Improvement of Streets Dunyapur | M/s Rising Sun Construction | 09/10/2007 | 270 | Works in progress |
| 11 | Widening and Improvement of Roads in P D Khan | M/s Malik Corporation. | 15/11/07 | 270 | Works in progress |
| 12 | Widening/Improvement of Roads in Lodhran | M/s Pyramid Construction. | 07/11/07 | 270 | Works in progress |
| 13 | Fire Fighting System Attock (Civil Works) | M/s Pyramid Construction. | 18/01/08 | 180 | Works in progress |
| 14 | Widening and Improvement of Roads in Daska | M/s Malik Corporation. | 21/01/08 | 330 | Works in progress |