Abstract of Sub-Projects Bhalwal.
Name of
Sub Project
|
: |
Improvement of Water Supply
|
Location
|
: |
Bhalwal |
|
Approved Cost
(Rs.) |
: |
68.21 Million |
Implementation Period
|
: |
18
Months |
Existing Situation:
Town is divided into
three zones.
Zone II
and III of this town have been provided with water
supply system and is working properly, while
Zone-I (project area is deficit of water supply
because of oldest system
All
distribution is rusted and leaking and production
is very less as compared with demand. People are
subjected to water shortage. Supply hours are very
less.
Very
low terminal pressure observed. water supplied to
consumers is contaminated due to out lived and
rusted distribution system laid in year 1927 and
some of it renovated in year 1964-65. Presently
population
covered 60 % and per capita supply is15 GPCD
against required 50 GPCD.
Description of Sub Project:
The sub
project comprises of tube wells, pumping
machinery, transmission main, distribution system,
over head reservoir, hypo chlorinators, bulk
meters and service connections.
The design horizon for the Project is upto
year 2025. However machinery and Transmission
mains are to be designed for period upto 2015 and
distribution network for year 2025. Additional
tube wells are to be installed along the left bank
of Lower Jhelum Canal (8 Nos.).
Sub Project Benefits:
•
Reduction of water-borne and communicable diseases
by provision of potable water.
•
Reduction in cost of curative medicine by
elimination / reduction of diseases.
•
Saving of man days of public presently affected
with such diseases.
•
Improvement of the working efficiency of
individuals and ultimately the organizations.
•
Improvement in general public health.
•
Raising the standard of living of the citizens.
•
Improve economic activity at the local level.